Logo of Phnom Penh Post newspaper Phnom Penh Post - 700MW plant 35% complete

700MW plant 35% complete

Content image - Phnom Penh Post
The $1 billion 700MW coal-fired power station in Preah Sihanouk province broke ground on December 18, 2019. Photo supplied

700MW plant 35% complete

Construction of a 700MW coal-fired power station representing $1 billion of capital investment in Preah Sihanouk province is 35 per cent complete since breaking ground on December 18, 2019.

Comprising two 350MW units, the project is a joint venture between local firm Cambodia International Investment and Development Group (CIIDG) and China Huadian Hong Kong Co Ltd (CHDHK).

Built on 54.9ha in Preah Sihanouk’s Stung Hav district, the facility is expected to be completed by the end of 2022 and be online in early 2023.

Victor Jona, director-general of the Ministry of Mines and Energy’s General Department of Energy, told The Post that the percentage of completion for the project was revealed in the latest joint report issued by the companies on December 30.

In their report, the companies considered factors such as impact handling, paper work and orders for equipment, he said.

“In my opinion, we will not have a problem with electricity supply in Cambodia over the next three years. Our investors have enough capital and they are very committed to developing the projects. I’ve seen companies with government investment concessions on power plants constantly moving forward,” Jona said.

The project was approved by the Council of Ministers in May 2018 under a build-own-operate-transfer (BOOT) concession for 35 years.

Preah Sihanouk Provincial Hall spokesman Kheang Phearum said development of the project has been smooth, expressing hope that it would be completed in the timeframe planned.

“Once the plant is online and connected to the national grid, it’ll dole out all the power needed in the provinces and” in Phnom Penh, he said.

The average power supply in Preah Sihanouk was between 83 and 85MW during the months of Covid-19, he added.

CIIDG already operates a $383 million coal-fired power plant in Preah Sihanouk province. The 270MW capacity plant was also split into two phases, with the second 135MW phase slated to be completed this year.

According to Jona, the Kingdom generates most of its energy from hydropower dams and coal-fired plants, accounting for around 36-40 per cent and 32 per cent of power production, respectively.

MOST VIEWED

  • Omicron patients can stay home: PM

    The Ministry of Health has issued a directive on the treatment of people who have tested positive for the highly transmissible Omicron coronavirus variant, following a suggestion from Prime Minister Hun Sen on the night of January 21. The directive permits home quarantine for those who

  • The effects of the USD interest rate hike on Cambodian economy

    Experts weigh in on the effect of a potential interest rate expansion by the US Federal Reserve on a highly dollarised Cambodia Anticipation of the US Federal Reserve’s interest rate hike in March is putting developing economies on edge, a recent blog post by

  • Cambodia’s first ever anime festival kicks off Jan 22 at capital’s F3 centre

    Phnom Penh's first ever Anime Festival will bring together fans, artists, shops and other local businesses with ties to the Japanese animation style for cosplay competitions, online games, pop-up shops and more on January 22, with Friends Futures Factory (F3) hosting. F3 is a project that

  • Hun Sen gets 4th Covid shot, urges compatriots to follow

    Prime Minister Hun Sen and his wife Bun Rany on January 14 received their fourth dose of Covid-19 vaccine and called on compatriots to follow suit as the Omicron coronavirus variant continues to spread in the community. This marks the launch of Cambodia's fourth-dose vaccination campaign,

  • Fourth dose Covid booster drive jabs 43K in two days

    In the first two days of the fourth-dose Covid-19 vaccination campaign, more than 43,000 people volunteered to get the jabs, while over 4.6 million people have received a third shot. Health ministry spokeswoman Or Vandine said that fourth-dose vaccinations, which began on January 14 exclusively with the Pfizer

  • Singapore backs Cambodia's efforts on Myanmar

    Singaporean Prime Minister Lee Hsien Loong supports Cambodia in its efforts to seek a solution to the ongoing Myanmar crisis as the chair of ASEAN. Lee expressed his support during a meeting with Prime Minister Hun Sen via videoconference on January 14, with the talks focused