Logo of Phnom Penh Post newspaper Phnom Penh Post - 700MW plant 35% complete

700MW plant 35% complete

Content image - Phnom Penh Post
The $1 billion 700MW coal-fired power station in Preah Sihanouk province broke ground on December 18, 2019. Photo supplied

700MW plant 35% complete

Construction of a 700MW coal-fired power station representing $1 billion of capital investment in Preah Sihanouk province is 35 per cent complete since breaking ground on December 18, 2019.

Comprising two 350MW units, the project is a joint venture between local firm Cambodia International Investment and Development Group (CIIDG) and China Huadian Hong Kong Co Ltd (CHDHK).

Built on 54.9ha in Preah Sihanouk’s Stung Hav district, the facility is expected to be completed by the end of 2022 and be online in early 2023.

Victor Jona, director-general of the Ministry of Mines and Energy’s General Department of Energy, told The Post that the percentage of completion for the project was revealed in the latest joint report issued by the companies on December 30.

In their report, the companies considered factors such as impact handling, paper work and orders for equipment, he said.

“In my opinion, we will not have a problem with electricity supply in Cambodia over the next three years. Our investors have enough capital and they are very committed to developing the projects. I’ve seen companies with government investment concessions on power plants constantly moving forward,” Jona said.

The project was approved by the Council of Ministers in May 2018 under a build-own-operate-transfer (BOOT) concession for 35 years.

Preah Sihanouk Provincial Hall spokesman Kheang Phearum said development of the project has been smooth, expressing hope that it would be completed in the timeframe planned.

“Once the plant is online and connected to the national grid, it’ll dole out all the power needed in the provinces and” in Phnom Penh, he said.

The average power supply in Preah Sihanouk was between 83 and 85MW during the months of Covid-19, he added.

CIIDG already operates a $383 million coal-fired power plant in Preah Sihanouk province. The 270MW capacity plant was also split into two phases, with the second 135MW phase slated to be completed this year.

According to Jona, the Kingdom generates most of its energy from hydropower dams and coal-fired plants, accounting for around 36-40 per cent and 32 per cent of power production, respectively.

MOST VIEWED

  • Angkor lifetime pass, special Siem Reap travel offers planned

    The Ministry of Tourism plans to introduce a convenient, single lifetime pass for foreign travellers to visit Angkor Archaeological Park and potentially other areas. The move is designed to stimulate tourism to the culturally rich province of Siem Reap as the start of the “Visit

  • Ice cream, noodles flagged over carcinogen

    The General Department of Customs and Excise of Cambodia (GDCE) has identified three types of instant noodles and ice cream trademarks originating from Thailand, Vietnam and France that are suspected to contain ethylene oxide, which poses a cancer risk to consumers. The general department has

  • Exclusive interview with Josep Borrell Fontelles, High Representative of the EU

    CAMBODIA is hosting the 55th ASEAN Foreign Ministers’ Meeting (AMM) and Related Meetings this week with top officials from the US, China, and Russia and other countries in the region slated to attend and to meet with face-to-face with their counterparts on the sidelines. In

  • Rise in Thai air routes to Siem Reap fuels travel hopes

    Local tourism industry players are eager for regional airline Bangkok Airways Pcl’s resumption of direct flight services between the Thai capital and Siem Reap town on August 1 – home of Cambodia’s awe-inspiring Angkor Archaeological Park – which is expected to boost the growth rate of

  • ASEAN Foreign Ministers’ meet commences, Taiwan issue possibly on table

    The 55th ASEAN Foreign Ministers’ Meeting (AMM) and related meetings hosted by Cambodia kicks off in Phnom Penh on August 3, with progress, challenges, and the way forward for the ASEAN Community-building on the table. Issues on Taiwan, sparked by the visit of US House Speaker

  • Recap of this year’s ASEAN FM meet and look ahead

    This year’s edition of the ASEAN Foreign Ministers’ Meeting (AMM) hosted by Cambodia comes against the backdrop of heightened global tensions and increasing rivalry between major powers that have been compared to the animosity of the Cold War era. The following is The Post’